Do Not Drag The Geomembrane During Transportation

Construction method:

The geomembrane should not be dragged forcibly during transportation to prevent sharp objects from puncturing. 

1. It should extend from the bottom to a high place, do not pull too tightly, and leave more than 1. 50% of the picture for local sinking and stretching. Considering the actual situation of this project, the slope is laid from top to bottom. 

2. The two adjacent longitudinal joints should not be on a horizontal line, and should be staggered by more than 1m from each other. 

3. The longitudinal joint should be more than 1. 50 meters away from the dam foot, and the bent foot should be located in the plane. 

4. First, the slope, then the bottom of the site. 

5. When laying on the slope, the film development direction should be basically parallel to the maximum slope line. 